Gas Powered Electricity Generation Plant

Gas Powered Electricity Generation Plant

Woodenbales civil section have now commenced work on the civicls package of a new gas powered electricity generation plant in Aberaman Industrial Park, Aberdare. After initially setting up the site, removing vegetation and clearing the site, the site strip is underway and the first layers of stone are being placed. The supervision of piling activities and installing the buried drainage services will follow before the shuttering and concrete pour of the 48m x 20m main slab comprising of reinforcement steel mesh and lose tied steel elements and 10 other ancillary bases can be carried out. Woodenbale will use in excess of 450m3 of concrete to complete the works with the main slab taking approx. 388m3 which will be a single pour. Service trenchs including water, BT, electrical & gas main feed for the plant will also be installed during the works.