Wiston Solar Farm HV Cable Trench

Following on from the successful completion of the Chapel Hill Solar Farm Woodenbale 2000 secured the contract for works to install the required cable trench on the Wiston Solar Farm project. This works involved the installation of 7500m of ducted cable trench from the solar farm site in Wiston to the sub-station west of Haverfordwest Golf Course on the A40. The route ran down the verge of the A40 where traffic control measures were taken before the route veers of the main road following the minor back roads to the site at Wiston. Many obstacles we overcome including existing services, a bridge and numerous road and driveway crossings. Woodenbale will also be installing the cable pull pits for the data cables following completion of the main trench.